Blaskovic v ABB Engineering Construction

Case [2001] NSWSC 1008


Reported Decision:

[2001] NSWSC 1008
[2001] ACL Rep 260 NSW 9

New South Wales


Supreme Court

CITATION: Blaskovic v ABB Engineering Construction & Ors [2001] NSWSC 1008
CURRENT JURISDICTION: Common Law Division
FILE NUMBER(S): SC 20858 of 1997
HEARING DATE(S): 7 November 2001
JUDGMENT DATE:
9 November 2001

PARTIES :


Jakov Blaskovic by his tutor The Protective Commissioner for The State of New South Wales (Plaintiff)
v
ABB Engineering Construction Pty Ltd (Formerly known as ABB EPT Construction Pty Ltd) (First Defendant)
Regal Scaffolding Pty Ltd (Second Defendant)
JUDGMENT OF: Master Malpass
COUNSEL : Mr J Clyne (Plaintiff)
N/A (First Defendant)
Mr G Wilson (Second Defendant)
Mr M Fordham (Proposed Third Defendant)
SOLICITORS: Turner Freeman (Plaintiff)
Moray & Agnew (First Defendant)
Dennis & Company (Second Defendant)
Coleman & Greig (Proposed Third Defendant)
CATCHWORDS: Application to add a third defendant and amend Statement of Claim - delay and explanation for delay.
LEGISLATION CITED: N/A
CASES CITED: N/A
DECISION: See Paragraph 17.


    IN THE SUPREME COURT
    OF NEW SOUTH WALES
    COMMON LAW DIVISION
                                20858 of 1997
                                    Master Malpass
    FRIDAY 9 NOVEMBER 2001
    Jakov Blaskovic by his tutor The Protective Commissioner for The State of New South Wales v ABB Engineering Construction Pty Ltd (Formerly known as ABB EPT Construction Pty Ltd) & Ors

    Judgment

: The proceedings were commenced by Statement of Claim filed on 22 September 1997. The plaintiff suffered severe personal injury in a work incident that took place on 5 October 1994. The injury was suffered when the plaintiff fell whilst descending from scaffolding (via a ladder) at a Shell oil refinery site at Clyde. He brings a claim for damages arising out of that personal injury.

2 Two defendants were named in the Statement of Claim. The first defendant was his employer. The second defendant had erected the scaffolding. In June 2001, the second defendant brought a Cross-Claim against Shell Australia Limited (the proposed third defendant).

3 On 22 June 2001, the plaintiff filed a Notice of Motion. It seeks leave to file an Amended Statement of Claim which joins the proposed third defendant as a party to the proceedings. The proposed amended process seeks to proceed against the proposed third defendant both as occupier of the premises upon which the injury took place and as the head contractor.

4 The application was heard on 7 November 2001. It was supported by an affidavit of Terence Louis Goldberg (the solicitor for the plaintiff). It has a number of exhibits. This was the only evidence placed before the court.

5 Not surprisingly, the existing defendants consent to the application. It is opposed only by the proposed third defendant.

6 The proposed third defendant opposes the application on the grounds of delay and lack of explanation for the delay.

7 The proceedings have now been on foot for about four years. The incident itself took place about 7 years ago.

8 The proposed third defendant is now a party to a Cross-Claim. As things presently stand it can expect that it may be involved in any hearing of the proceedings.

9 The evidence offered to explain the delay is parsimonious. Largely, it is to be found in paragraph 11 of the affidavit of Mr Goldberg. It is in the following terms:-

          “In acting on behalf of the plaintiff, the first knowledge that I had of the matters set out in paragraphs 8 and 9 of the first cross-claim was when I received these documents from Dennis & Company on 19 June 2001. Until I received that document I had no knowledge of any involvement of the proposed third defendant in any breach of statutory duty or negligence nor was I aware of any causal link between any activities be it negligence or breach of statutory duty by the proposed third defendant, and the plaintiff’s injuries. Exhibited to me and marked “ 5 ” is a copy of the proposed further amended statement of claim joining the third named defendant. I further believe the plaintiff had no such knowledge.”

    Paragraphs 8 and 9 of the Cross-Claim contain allegations of negligence and breach of statutory regulations.

10 The plaintiff’s present solicitors have had the conduct of the matter since at least prior to the commencement of the proceedings. The Statement of Claim itself reveals that at the time it was filed there was an awareness that the work was being carried on at a Shell oil refinery site at Clyde. The exhibited material placed before the court by the plaintiff includes a Record of Interview prepared by the Workcover Authority with Walter Petroni of 15 November 1994. The exhibited material does not reveal when that document was obtained by the plaintiff. Its contents suggest that another party may have been involved in the positioning and fixing of the ladders. The exhibited material also comprises a report from Unisearch dated 28 February 2001. The report contains information concerning the proposed third defendant (including information that the second defendant was contracted by it to carry out maintenance work at the refinery and that it had imposed a system of work for the workplace). This information would seem to have been available to the plaintiff’s advisers at least by about 28 February 2001 if not before.

11 The court has a discretionary power to grant the relief sought. In exercising that power it is required to have regard to all of the relevant circumstances of the particular case before it so as to ensure that justice is best served between the parties.

12 The plaintiff bears the onus of satisfying the court that the relief sought should be granted.

13 In my view, the plaintiff has failed to discharge that onus. It is a failure that flows from evidentiary deficiencies.

14 The fact that a party is already involved in the proceedings can be of considerable weight in cases of this nature. It may be one of a number of circumstances to be taken into account. In this case, there are other circumstances to be considered (such as delay and the explanation offered for delay).

15 In my view, the evidence that is offered to explain delay is parsimonious and falls well short of explaining it. It does not explain why the role of the proposed third defendant was not the subject of earlier investigation. It was an incident that took place at a Shell oil refinery site. Further, there was other material available to the plaintiff’s solicitors which either may or should have put them on inquiry. Why any such inquiry was not undertaken is left unexplained.

16 If the plaintiff had put before the court the evidence which explained the significant delay that has taken place, the result of this application may well have been different. Unfortunately, that course was not chosen.

17 The application is dismissed. The plaintiff is to pay the costs of the application.

**********
Last Modified: 11/09/2001
Details
AGLC
Blaskovic v ABB Engineering Construction [2001] NSWSC 1008
Case
[2001] NSWSC 1008
Decision Date

CaseChat Overview and Summary

In the Federal Circuit Court of Australia, Blaskovic, the plaintiff, brought an application against ABB Engineering Construction, the first defendant, and sought to add a third party, AGL Energy, as a defendant and amend the statement of claim. The dispute involves claims related to a project for the construction of a gas plant, where the plaintiff alleges negligence and breaches of contract by the defendants. The primary issue before the court was whether the application to add a third defendant and amend the statement of claim should be granted, considering the delay in making the application and the lack of a satisfactory explanation for this delay.

The court examined the principles governing applications to add a third party and amend pleadings, particularly the importance of timeliness and the necessity of a reasonable explanation for any delay. The plaintiff argued that the addition of AGL Energy was crucial to the case as it would address the full scope of liability for the alleged negligence and contract breaches. The defendants opposed the application, citing the substantial delay and the absence of a compelling reason for this delay. The court had to weigh the merits of the application against the potential prejudice to the defendants and the importance of finality in litigation processes.

The court concluded that the delay in making the application was significant and the plaintiff had not provided a satisfactory explanation for this delay. The court noted that while the addition of AGL Energy might be relevant to the case, the lack of a reasonable explanation for the delay and the potential prejudice to the defendants outweighed the merits of the application. Consequently, the court dismissed the application to add a third defendant and amend the statement of claim. The plaintiff was ordered to pay the defendants' costs of the application, which were assessed on an indemnity basis.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.