IN THE HIGH COURT OF NEW ZEALAND NAPIER REGISTRY
I TE KŌTI MATUA O AOTEAROA AHURIRI ROHE
CIV-2021-441-42
[2021] NZHC 2319
UNDER the Unit Titles Act 2010 IN THE MATTER OF
an order settling scheme under s 74
BETWEEN
BODY CORPORATE 343200
Applicant
AND
JOHN CHARLES PENNINGTON DUNCAN, COLLEEN GAENOR DUNCAN & ORS
First Respondents
LUAN SIXTUS CUFFE
Second Respondent
ANZ BANK OF NEW ZEALAND LIMITED
Third Respondent
BANK OF NEW ZEALAND
Fourth Respondent
Hearing (by AVL): 6 September 2021 Counsel:
C Baker for the Applicant
No appearance for the Respondents
Judgment:
6 September 2021
ORAL JUDGMENT OF GWYN J
[1] The applicant is the Body Corporate of an eight-unit complex at 101 Marine Parade, Napier, known as the T & G Building. It applies for an order under s 74 of the Unit Titles Act 2010 (the Act) to settle a scheme of repair (the Scheme).
BODY CORPORATE 343200 v DUNCAN [2021] NZHC 2319 [6 September 2021]
[2] The Body Corporate has served the application on all those with an interest in the units (all owners of the units and any mortgagees and charge-holders) and the insurers of the building. No opposition to the application has been filed. A motion to file an application under s 74 of the Act was put to an Extraordinary General Meeting (EGM) on 6 April 2021. All eight units were represented at the meeting, in person, by proxy, or by postal vote. Approval for the resolution to apply for the Scheme was unanimous amongst the attendees.
[3]In those circumstances, the applicant seeks orders today.
Discussion
[4] The Court of Appeal in Tisch v Body Corporate 318596 set out the three steps the Court must follow when considering an application to settle a scheme under s 74 of the Act:1
(a)The Court must be satisfied that the building has been damaged or destroyed.
(b)If so satisfied, the Court must decide whether a scheme is appropriate in the circumstances.
(c)If a scheme is appropriate, the Court must then decide what its terms should be.
[5] I have considered the affidavit evidence put before the Court, which includes evidence as to the damage to the building and attaches the proposed Scheme. I am satisfied that the building has been damaged and is in need of repair. I am also satisfied that a scheme is appropriate in all the circumstances.
[6] The Court of Appeal in Tisch set out five factors that must be considered at the third step in the process:2
1 Tisch v Body Corporate No. 318596 [2011] NZCA 420, [2011] NZLR 679 at [35]. There the Court was considering s 48 of the Unit Titles Act 1972, the predecessor to s 74 of the Act.
2 At [44]-[49].
(a)a scheme with broad support is preferred;
(b)the scheme is to be appropriately detailed;
(c)the order can have retrospective effect, as long as the Body Corporate has acted in accordance with the scheme prior to the Court’s approval;
(d)normally work is to be done to the same standard and at the same time; and
(e)the terms of the scheme are not to depart from the Act and the Body Corporate Rules any more than reasonably necessary to achieve fairness between unit holders in the circumstances.
[7] I am satisfied that all five of those requirements have been met. I have already referred to the support for the Scheme which was evident at the EGM. As indicated, I have considered the Scheme and I am satisfied it has the level of detail necessary and is in substantially similar terms to schemes which have been approved by this Court on prior occasions.
[8] I am also satisfied as to the basis of the funding to be raised in connection with the Scheme and of the standard of repair: the work is to be carried out by a single contractor, under the control of a single consultant, at the same time. Furthermore, the Scheme departs no more than necessary from the Act and the Body Corporate Rules. There is nothing in the Scheme which suggests to me that the interests of any unit holder or mortgagee are adversely affected.
[9] For those reasons, the application is granted and the Scheme is approved. I grant the orders sought at 1.1-1.4 inclusive of the applicant’s originating application dated 10 June 2021.
Gwyn J
Solicitors:
Price Baker Berridge, Henderson
- AGLC
- Body Corporate 343200 v Duncan [2021] NZHC 2319
- Case
- [2021] NZHC 2319
- Decision Date
CaseChat Overview and Summary
The court reviewed the affidavit evidence presented, which confirmed the building's damage and the necessity for repairs. The court followed the three-step process outlined by the Court of Appeal in Tisch v Body Corporate 318596 for approving a scheme under section 74 of the Act. The court found the proposed scheme to be appropriately detailed and in line with previous approvals, ensuring a single contractor and consultant would perform the repairs to a consistent standard. The funding basis and repair standards were deemed adequate, and the scheme was seen as fair to all unit holders and mortgagees, without unduly deviating from the Act or Body Corporate Rules.
In light of these findings, the court granted the application and approved the scheme, thereby authorizing the Body Corporate to proceed with the repairs as outlined. The orders were issued in accordance with the applicant’s originating application dated 10 June 2021, ensuring the scheme could be implemented effectively.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.